Data Centers Keep Rising as Local Governments Hit Pause: The U.S., California, the Bay Area and San Joaquin County

Data Centers Keep Rising as Local Governments Hit Pause: The U.S., California, the Bay Area and San Joaquin County | LodiEye

At a Glance

Construction kept going. Local brakes multiplied. Builders started 4.6 gigawatts of new data-center capacity in October, the second-largest month on Cleanview’s record. Over the same weeks, cities and counties from Loudoun County, Virginia, to San Joaquin County adopted pauses on new approvals.

  • Nationally, hundreds of campuses remain under construction, while Relae counted 16 projects stopped by community opposition in July through September and Programs.com listed six large cancellations from September through November. The two lists can overlap.
  • California has little new construction. Cleanview lists five campuses under construction. Power access, not water, is the binding limit on the projects already in line.
  • The Bay Area adopted the most local pauses, but most of them cover places with no pending applications. San Jose’s pause is the exception: it holds 12 proposals.
  • San Joaquin County has no data-center applications, yet extended its pause on Nov. 17 for 10 months and 15 days while staff study power, groundwater and community effects. Lodi has no application either.
4.6 GWU.S. capacity that started construction in October, in 33 buildings
281U.S. campuses under construction as of mid-November
16U.S. projects stopped by community opposition, July–Sept.
11 of 16Of those stops came from a government denial or zoning ban
5California campuses under construction
240 MWOf PG&E’s 12,870 MW data-center pipeline in the construction stage
12San Jose proposals held by the city’s Nov. 17 pause
0Data-center applications pending in unincorporated San Joaquin County

Sources for each figure appear in the sections below. The national figures come from different trackers that count different things; the next section explains why they cannot be combined into one ratio.

How to Read the Counts

No public agency keeps a national list of data centers that are moving or stopped. Private trackers fill the gap, and each counts a different unit. Cleanview uses satellite images to record a “start” when a building rises vertically, and measures size in power capacity.[1] Relae counts projects that community opposition blocked, withdrew or stalled, and calls its count a conservative lower bound.[4] Programs.com lists only cancellations of at least 100 megawatts or $1 billion.[6]

Because one counts buildings, one counts projects and one counts only the largest cancellations, LodiEye reports each number separately and does not divide one by another to produce a “percent blocked.”

Megawatt (MW) and gigawatt (GW)
Units of electric power. One gigawatt equals 1,000 megawatts. Data centers are sized by how much power they can draw, not by square feet.
Moratorium or pause
A temporary local law that stops a city or county from accepting or approving certain applications. In California, Government Code section 65858 allows a 45-day urgency moratorium that a four-fifths vote can extend, first by 10 months and 15 days.
Unincorporated area
Land outside any city’s limits, where the county is the land-use authority. A county moratorium does not apply inside a city such as Lodi or Stockton.
Interconnection and energization
The utility process that connects a large customer to the grid and then turns the power on. A project can hold every local permit and still wait years for this step.
Hyperscale
The largest class of data center, typically built for cloud or artificial-intelligence companies and drawing tens or hundreds of megawatts.

The National Picture: Construction Continues

Cleanview counted 8.4 GW of construction starts in 65 buildings from July through September, down 28% from 11.7 GW in 96 buildings in April through June, but 55% above the same quarter of 2025. October alone added 4.6 GW in 33 buildings, nearly double October 2025’s 2.4 GW.[1][2]

U.S. Data-Center Construction Starts, in Gigawatts

Source: Cleanview Q3 2026 construction brief. October is one month; the other two bars are three-month quarters. Building counts: 96, 65 and 33.

Three projects supplied about 35% of the quarter’s capacity: a 720 MW campus in Monarch, West Virginia; a 461 MW Stargate campus in Saline Township, Michigan; and a 450 MW Crusoe campus in Abilene, Texas.[1] The quarterly dip reflects a few very large projects starting in spring, not a collapse.

Cleanview reported 38 GW of starts in the 12 months through October, double the prior 12 months, with 58 GW under construction and 65 GW operating.[1] By campus, the Urban Land Institute, citing Cleanview, counted 578 operating, 281 under construction and 707 planned as of Nov. 16.[3] Rystad Energy found that about half of the capacity expected for 2027 and 2028 is already under construction or under a roof, and expects slow construction, not opposition, to push about one-third of it past its planned year.[7]

What Stopped Projects, and Why

Relae counted 16 U.S. projects stopped by community opposition from July through September, up from seven in the same quarter of 2025, representing about $64 billion. Its total since January 2024 reached 70 projects and about $271 billion.[4] The bigger change was who stopped them.

How the 16 Stopped Projects Ended, July–September 2026

Source: Relae, Community Signals Q3 2026. Red bars mark direct government action.

Local governments ended 11 of the 16 directly, through seven formal denials and four zoning bans. In the previous quarter, government action ended three of 15; most projects then ended because a developer withdrew, often shortly before a hearing.[4] Heatmap Pro tallied at least $260 billion in projects canceled in 2026, about $130 billion of it in July through September.[5]

Programs.com, which lists only cancellations of at least 100 MW or $1 billion, added six from September through November 22: Henderson, Nevada (withdrawn, September); Archbald, Pennsylvania; Wisconsin Rapids, Wisconsin (both denied, October); Concord Township, Iowa; Brighton, Colorado (both withdrawn, October); and Delhi Township, Michigan (withdrawn, November).[6]

Law versus power versus water

Readers asked which projects are blocked by legislation and which by power or water. The record shows a clear pattern: laws and votes do the blocking; power shortages do the delaying; water is a common concern but rarely the decisive one. Relae found water raised in 32 of 44 cases it studied in depth but as the leading concern in only one, San Marcos, Texas. Energy costs and the grid appeared as a leading or secondary concern in 29.[4]

Major National Holds Active in the Last 90 Days
Where What happened Type Status
Texas (ERCOT grid) After Gov. Greg Abbott’s Aug. 3 directive, the grid operator stopped approving power-on for new data centers and crypto mines of 75 MW or more until an audit and community-impact review finish.[8] Rystad estimates 1.5 to 3 GW of Texas projects face delay.[7] Power Government order ERCOT reports due Dec. 10
Loudoun County, Va. On Nov. 17 the Board of Supervisors paused action on legislative data-center and substation applications for up to 12 months, retroactive to Sept. 15, while it rewrites its data-center rules.[9] Legislation In effect
Six large cancellations Two denials and four withdrawals listed by Programs.com, September through November.[6] Local vote / withdrawn Ended

The Texas hold mixes categories: a government order stopped grid connections, and the audit asks about grid dependence and, after a Sept. 14 follow-up directive, water use.

California: New State Rules, Little New Construction

Gov. Gavin Newsom signed seven data-center bills on Sept. 21. Most take effect Jan. 1, 2027. They require disclosure and planning; none bans data centers.[10][11]

California’s Seven New Data-Center Laws
Bill What it requires Area
AB 1577 Data centers of 10 MW or more report energy information to the California Energy Commission. Power
AB 2383 Sets rules for electric tariffs (utility rate schedules) for large data-center customers. Power
AB 2469 Requires a water-supply assessment before local permits; begins Jan. 1, 2028. Water
AB 2619 Requires water-use estimates to the local water supplier before a business license. Water
SB 886 Ratepayer Protection Act. The California Public Utilities Commission (CPUC) must adopt data-center tariffs by Jan. 1, 2028, with a 10-year minimum term and an early-termination fee. Power
SB 887 Bars categorical exemptions from the California Environmental Quality Act (CEQA) for data centers, with an expedited path for qualifying projects. Land use
SB 1168 Addresses electric rate structures for large loads. Power

Summaries from the Governor’s Office and Foley & Lardner. Readers can check bill text at leginfo.legislature.ca.gov.

Local officials did not wait for those laws. CalMatters, citing Food & Water Watch, counted at least 26 California resolutions, moratoriums or bans passed or proposed from June to late October.[12]

How much is being built

Counts of California data centers vary with the definition. Cleanview lists 143 data centers on 98 campuses: 69 campuses operating, five under construction and 24 planned. By building, it counts 100 operating, seven under construction and 36 planned. The largest under construction are Amazon Web Services in Gilroy, Stack’s SVY03A in Alameda County and Digital Realty’s SJC37.[13] The California Energy Commission counted more than 200 active data centers drawing about 1,000 MW in early 2026, roughly 2% of peak demand on the state’s main grid.[30]

Power is the bottleneck

PG&E, the utility serving most of Northern California outside cities with their own electric departments, reported a data-center pipeline of 12.87 GW at the end of September, up from 12.71 GW in June and 5.1 GW in March. Only 240 MW sits in the construction stage. PG&E has connected 174 MW of data-center load since 2024.[14]

PG&E Data-Center Pipeline by Stage, Sept. 30, 2026 (MW)

Source: PG&E third-quarter 2026 results, as reported by DatacenterDynamics. Total: 12,870 MW.

Less than 2% of PG&E’s pipeline is in construction. In Santa Clara, the city-owned utility Silicon Valley Power stopped taking new data-center hookup requests in 2023 because it could not supply more large users. Two approved data centers are under construction there, and eight more approved before the cutoff are waiting for electricity. Data centers use about 54% of the city’s power.[15]

The state’s first CPUC vote on a PG&E data-center power agreement also slipped. The commission’s draft would approve service for a 250 MW Google load in North San Jose if Google advances an extra $600,000 per megawatt, about $150 million. On Nov. 19 the commission held the item again, to Jan. 14, 2027, after repeated holds since August.[16][17]

The Bay Area: Pauses Everywhere, Few Projects Affected

The Bay Area adopted more local pauses than any other part of the state this fall. Counting ordinances overstates their effect, so the table below lists what each pause actually holds.

Bay Area Data-Center Pauses in Effect, Nov. 22, 2026
Jurisdiction Action Runs through Projects held
San Jose Unanimous Nov. 17 pause on land-use approvals for data centers and other large energy users. Proposed standards go to the City Council Dec. 8.[18] Until standards adopted 12 proposals
San Francisco Supervisors unanimously extended the citywide pause on Nov. 17 by 10 months and 15 days.[19] A planned NOVVA expansion at 400 Paul Ave. from 9 to 36 MW is on hold.[21] About Sept. 2027 No pending applications
Oakland Council unanimously extended its pause on Nov. 10.[22] Oct. 5, 2027 Not reported
San Mateo County Unanimous 45-day urgency pause on Nov. 17 for unincorporated areas, after a July inquiry about the county Event Center site.[23] Early Jan. 2027 unless extended Inquiry only
Richmond Extended its pause in October.[24] Sept. 15, 2028 None
Gilroy Council unanimously extended its pause Oct. 19.[25] The AWS campus approved July 3, 2025, is exempt and under construction.[26] Sept. 3, 2027 None; AWS continues
Hayward Adopted a 45-day pause Oct. 20.[27] Early Dec. unless extended Not reported
Oakley Pause reported by a secondary tracker.[28] Apr. 14, 2027 (secondary) Not reported

“Early” end dates are LodiEye’s arithmetic from the 45-day adoption date. Santa Clara chose stricter rules instead of a pause.[15] Dublin is considering one.[29]

San Francisco shows how a legal pause and a power limit work together. A Planning Department report found the city’s transmission capacity is 1,000 MW. Peak use reached 900 MW in 2019, fell during the pandemic and returned to 800 MW in 2025, and staff expect peak demand to grow at least 20 MW a year without any new data centers.[20]

San Francisco Peak Electricity Use Against Its Transmission Limit (MW)

Source: San Francisco Planning Department report, as reported by The San Francisco Standard.

The same report estimated the highest daily water use by the city’s data centers at 35,000 gallons, “within the range of other large development projects.”[20] In San Francisco, the moratorium is the legal tool and power is the underlying constraint. Water is a secondary question.

San Joaquin County: A Pause Before Any Proposal

San Joaquin County acted before any developer applied. A Sept. 1 letter from Supervisor Robert Rickman noted that the county’s Development Title does not list data centers as an allowed use and that the county has no such facilities or applications.[31]

San Joaquin County Data-Center Actions, 2026
Date Action
Sept. 2 Board directed staff to study large-scale AI data centers and asked County Counsel whether a temporary moratorium was legal.[32]
Oct. 6 Board voted 5-0 for a 45-day urgency ordinance stopping land-use approvals for new data centers in unincorporated areas.[33][30]
Nov. 10 Extension vote postponed. It needed four of five votes, and two supervisors were absent.[34]
Nov. 17 Board extended the pause for hyperscale data centers by 10 months and 15 days. The Community Development Department will study other jurisdictions’ rules and resource demands, run public outreach and hire a consultant, with a full report due June 2027.[35]

The county announcement does not state an end date. Adding 45 days and 10 months 15 days to Oct. 6 places it in early October 2027, the same schedule as Oakland’s.

What the pause covers

The ordinance applies to general plan and zoning amendments, use permits, variances, parcel and final maps, and building or grading permits that would allow a qualifying data center. It exempts smaller server rooms serving hospitals, schools or individual businesses, telecommunications facilities, government emergency-communications sites and facilities owned by public utilities.[30]

Community Development Director Jennifer Jolly told supervisors the county has no formal data-center application. Two specific plans under county review list data centers as a possible future use, and she had met with one person interested in developing one. If either plan is approved before permanent rules, its applicant must agree to follow them.[30]

Why water ranks higher here

Water carries more weight in San Joaquin County than in San Francisco. Jolly cited parts of the county within the critically overdrafted Eastern San Joaquin Groundwater Basin and the Tracy Subbasin, along with grid strain, power costs for residents, emergency response, heat, noise and diesel backup generators.[30] “Critically overdrafted” is the state’s term for a basin where pumping exceeds natural recharge enough to cause lasting harm; such basins must follow a sustainability plan under the Sustainable Groundwater Management Act.

Stockton

Stockton has not adopted a pause. On Sept. 1 the City Council voted 7-0 to remove data centers from its 2026–28 economic development plan while staff hold listening sessions.[30] The city scheduled sessions for Nov. 6, Nov. 9 and Dec. 2.[36] Stockton already has one data center: Nautilus Data Technologies’ 6.5 MW facility at the Port of Stockton, operating since 2021, which circulates San Joaquin River water for cooling.[30]

Lodi

Lodi has no data-center application. At a May council meeting, Council Member Cameron Bregman said no plans existed but that he had become more open to a data center near the White Slough Water Pollution Control Facility west of Interstate 5. City staff said the White Slough property covers 1,040 acres, about 220 of them available for development, and about 130 of those could go to a proposed PG&E research site.[37]

Lodi runs its own electric utility, so a Lodi data center would depend on Lodi Electric and the Northern California Power Agency (NCPA), the public power agency that co-owns the Lodi Energy Center, rather than PG&E retail service. Electric Utility Director Jeff Berkheimer told the council, “There’s not currently the electric distribution system available for us to offer data center service out there,” and said NCPA would first need to study transmission congestion.[37]

On Nov. 16, columnist Steve Mann reported that former Mayor Jack Sieglock wants the city to take a second look, with profits returned through customer bill credits and treated wastewater used for cooling. Mann also wrote that Bregman reversed his position after pushback.[38] LodiEye tested that idea in a separate report, which found that credits, water and power all depend on numbers no one has yet put on the record.[39]

Does the county pause reach Lodi? Not inside city limits. The county ordinance covers unincorporated land only. Any White Slough parcel would need a parcel-level check: if it lies inside Lodi’s limits, the city, not the county, would decide land use. LodiEye has not yet confirmed each parcel’s jurisdiction against county assessor records.

The Scorecard: Law, Power or Water

The table sorts each California and local case by the tool that actually holds it and the constraint behind it.

What Holds Data Centers in California and San Joaquin County
Place Binding tool Underlying constraint Effect today
San Jose Local pause Power, water, generators, labor standards 12 proposals held
Santa Clara Utility hookup cutoff Silicon Valley Power capacity 8 approved projects waiting for power
Google, North San Jose State utility approval Who pays for grid upgrades CPUC vote held to Jan. 14, 2027
PG&E territory Interconnection queue Engineering and construction of grid upgrades 240 of 12,870 MW in construction
San Francisco Local pause Grid near its 1,000 MW limit No applications; one expansion on hold
Gilroy Local pause Power, water, generator emissions, noise New applications stopped; AWS building
San Joaquin County Local pause Groundwater, grid, power costs, noise No applications held
Lodi None No distribution capacity at White Slough today No application
California statewide Disclosure laws Water-supply and energy reporting Takes effect 2027–28; no ban

No California project in this period was denied because a water supplier said it could not serve it. Power access holds back the projects that exist, and local pauses mostly apply where no project exists yet.

What to Watch, With Links

LodiEye is the original civic-reporting and analysis arm of Lodi411.com, a citizen-run civic data and transparency platform serving Lodi, California and San Joaquin County. LodiEye gathers information of public interest, applies editorial judgment to public records, meetings, and data, and publishes original explanatory reporting for its readers — the work of a newsroom, and a representative of the news media as that term is defined under federal law. Our reporting emphasizes primary sources, public data, and full source transparency so readers can check every claim. LodiEye complements, and does not replace, the other outlets covering this region; for additional reporting on Lodi, San Joaquin County, and the broader region, we also encourage readers to consult the Lodi News-Sentinel, Stocktonia, The Sacramento Bee, CalMatters, and other established news organizations. Our full editorial standards and news-media-status statement is published at lodi411.com/editorial-standards.

This LodiEye analysis was produced using artificial intelligence tools under the direction and review of the founder. Lodi411 uses multiple AI platforms in its research and publication workflow, including Anthropic’s Claude (primarily Opus and Sonnet models) and Perplexity AI across a variety of large language models offered by each. These tools were used in the following capacities:

Source Discovery: AI-assisted search gathered 39 sources: county, city, state, utility-commission and grid-operator records; three private construction and cancellation trackers (Cleanview, Relae and Programs.com); energy-research firms; and regional news outlets including Stocktonia, the Lodi News-Sentinel, The San Francisco Standard, KQED and CalMatters. Perplexity AI handled discovery and real-time retrieval.

Credibility Validation: Government records and agency announcements took priority, followed by tracker data, then news reports. Where counts conflicted, as with California’s total number of data centers, the report names each source’s definition rather than choosing one silently. Figures available only from secondary trackers, such as Oakley’s end date, are labeled.

Analysis and Synthesis: The AI tools sorted each hold by its binding tool (local law, utility queue, state approval) and by its underlying constraint (power, water, other). That framework produced the scorecard table. The report does not compute a national blocked-versus-moving ratio because the trackers count different units.

Presentation: AI tools drafted and formatted the report, built the four Kendo UI charts and accessible tables, and wrote plain-language definitions of civic and utility terms.

Final Review: Multiple AI models reviewed the draft for factual consistency, source attribution and balance. Throughout the process, the editor sets the report’s goals, scope, and tone; creates and shapes draft content; reviews and edits the report; integrates independent fact checks; and reviews the AI cross-checks and validations. Multi-tool cross-checking across independent models and sources is the primary error-reduction mechanism. This is a publication draft; ordinance texts and parcel jurisdiction at White Slough remain for documentary verification.

Lodi411/LodiEye believes transparency about how our research is produced strengthens trust with readers. Readers who spot an error are encouraged to write editor@lodi411.com so we can correct it.

References

Bracketed numbers in the text link directly to these sources. Government records are the source of record where available.

  1. Cleanview, “Data center construction just slowed,” November 2026https://newsletter.cleanview.co/p/data-center-construction-just-slowed
  2. Cleanview, Data Center Construction Brief, Q3 2026https://cleanview.co/reports/data-center-construction-brief-q3-2026
  3. Urban Land Institute, “Data Center Expansion Under Pressure,” Nov. 16, 2026https://urbanland.uli.org/capital-markets-and-finance/data-center-expansion-under-pressure
  4. Relae, “Community Signals Q3 2026,” Nov. 17, 2026https://relae.co/blog/community-signals-q3-2026-data-center-cancellations
  5. Heatmap News, $260 billion in data-center cancellationshttps://heatmap.news/daily/260-billion-data-center-opposition
  6. Programs.com, Data Center Project Cancellation Tracker (updated Nov. 22, 2026)https://programs.com/resources/data-center-project-tracker/
  7. Rystad Energy, U.S. data-center growth outlook, Nov. 19, 2026https://www.rystadenergy.com/insights/blue-wave-likely-to-change-terms-of-us-data-center-growth-but-not-the-pace
  8. ERCOT, Batch Zero Update (board item 14)https://www.ercot.com/files/docs/2026/09/11/14-Batch-Zero-Update.pdf
  9. Loudoun County, “Loudoun Board Pauses Legislative Data Center & Substation Applications”https://www.loudoun.gov/m/NewsFlash/home/detail/10993
  10. Office of the Governor, data-center bill signing, Sept. 21, 2026https://www.gov.ca.gov/2026/09/21/governor-newsom-signs-most-comprehensive-data-center-laws-in-the-nation-providing-communities-more-control-on-water-electricity-and-land-use/
  11. Foley & Lardner, “California Enacts Seven Data Center Bills”https://www.foley.com/insights/publications/2026/09/california-enacts-seven-data-center-bills-effective-january-1-2027-new-tariff-entitlement-and-disclosure-rules-for-hyperscalers-developers-and-power-producers/
  12. CalMatters via AP, “California cities pull the plug on data centers,” Oct. 23, 2026https://apnews.com/article/data-centers-california-transparency-cities-moratoriums-3198ddfeb5e91b68ca313798d4f90ee5
  13. Cleanview, California data centers (accessed Nov. 22, 2026)https://cleanview.co/data-centers/california
  14. DatacenterDynamics, “PG&E sees marginal increase in data center pipeline”https://www.datacenterdynamics.com/en/news/pge-sees-marginal-increase-in-data-center-pipeline/
  15. KQED, “Santa Clara, California’s Capital of Data Centers, Weighs More Regulations”https://www.kqed.org/news/12103316/santa-clara-californias-capital-of-data-centers-weighs-more-regulations
  16. CPUC, Nov. 19, 2026 voting meeting results (Agenda 3590)https://ia.cpuc.ca.gov/agendadocs/3590_results.csv
  17. CPUC, Draft Resolution E-5455 (PG&E–Google)https://docs.cpuc.ca.gov/PublishedDocs/Published/G000/M627/K943/627943892.docx
  18. San José Spotlight, “San Jose enacts temporary data center moratorium”https://sanjosespotlight.com/san-jose-enacts-temporary-data-center-moratorium/
  19. The San Francisco Standard, moratorium extension, Nov. 17, 2026https://sfstandard.com/2026/11/17/data-center-moratorium-september-2027/
  20. The San Francisco Standard, “San Francisco’s power grid is nearly maxed out,” Nov. 16, 2026https://sfstandard.com/2026/11/16/data-center-moratorium-power-grid/
  21. SFist, supervisors extend data-center moratorium, Nov. 17, 2026https://sfist.com/2026/11/17/sf-supervisors-extend-data-center-moratorium-citing-gaps-in-environmental-impact-report/
  22. The Oaklandside, Oakland moratorium extension, Nov. 10, 2026https://oaklandside.org/2026/11/10/oakland-data-center-moratorium-extension/
  23. The Almanac, “San Mateo County temporarily bans new data centers”https://www.almanacnews.com/san-mateo-county/2026/11/19/san-mateo-county-temporarily-bans-new-data-centers/
  24. CEQAnet, City of Richmond data-center moratorium extension noticehttps://ceqanet.lci.ca.gov/2026101044
  25. Gilroy Dispatch, “City Council extends Gilroy’s moratorium on data centers”https://gilroydispatch.com/city-council-extends-gilroys-moratorium-on-data-centers/
  26. City of Gilroy, Gilroy Data Center (by Amazon Web Services)https://www.cityofgilroy.org/1019/Gilroy-Data-Center-by-AWS
  27. East Bay Times, Hayward pauses new data centers, Oct. 21, 2026https://www.eastbaytimes.com/2026/10/21/put-the-heart-back-in-the-heart-of-the-bay-hayward-puts-pause-on-new-data-centers/
  28. Houseberry, Bay Area data-center moratoriums tracker (secondary source)https://www.houseberry.com/blog/bay-area-data-center-moratoriums-tracker-gilroy-extension/
  29. The Mercury News, Dublin considers a moratorium, Nov. 18, 2026https://www.siliconvalley.com/2026/11/18/other-bay-area-cities-have-data-center-moratoriums-now-dublin-wants-one/
  30. Stocktonia, “San Joaquin County halts new data center approvals amid water, power concerns,” Oct. 7, 2026https://stocktonia.org/news/business/2026/10/07/san-joaquin-county-halts-new-data-center-approvals-amid-water-power-concerns/
  31. San Joaquin County, Supervisor Rickman board letter on data centershttps://www.sjgov.org/docs/default-source/board-of-supervisors/district-5/links/Board-Letter-Data-Center.pdf
  32. San Joaquin County, Board moves to address impacts of large-scale AI data centers, Sept. 2, 2026https://www.sjgov.org/department/bos/board-news/board-news-detail/2026/09/02/sjc-board-moves-to-address-impacts-of-large-scale-ai-data-centers
  33. San Joaquin County, Board adopts 45-day moratorium, Oct. 7, 2026https://www.sanjoaquin.gov/department/bos/board-news/board-news-detail/2026/10/07/board-adopts-45-day-moratorium-on-land-approvals-for-new-data-centers
  34. Stocktonia, county aims to extend data-center ban, Nov. 13, 2026https://stocktonia.org/news/local-government/2026/11/13/san-joaquin-county-aims-to-extend-data-center-ban-to-permit-deeper-study/
  35. San Joaquin County, Board extends AI data center moratorium, Nov. 17, 2026https://www.sjgov.org/department/bos/board-news/board-news-detail/2026/11/17/board-extends-ai-data-center-moratorium-to-evaluate-environmental-community-impact
  36. Stocktonia, Stockton data-center listening sessions, Nov. 6, 2026https://stocktonia.org/news/local-government/2026/11/06/stockton-data-center-listening-sessions/
  37. Lodi News-Sentinel, “The data debate powers up in Lodi,” May 9, 2026https://www.lodinews.com/news/article_7575bf76-0840-4f87-aa88-68c9e522bb6a.html
  38. Steve Mann, “Datacenters,” About Town, Nov. 16, 2026https://stevemann.substack.com/p/datacentersOpinion column; source for Sieglock’s proposal, not a project record.
  39. LodiEye, “White Slough Data Center: A Second Look Needs Better Numbers” (related analysis)https://lodi411.com/lodi-eye/white-slough-data-center-a-second-look-needs-better-numbers

Questions or corrections: editor@lodi411.com